闵浦大桥浦西段上横梁底模支撑桁架设计与施工
  • 作者: 周 涛 杨兴富 陶利峰等
论文摘要
[摘要] 由于施工前期动迁延误等原因,闵浦大桥浦西段施工进度比浦东段落后3个月。为保证2009年底通车总体目标,采用底部设置钢桁架作为底模支撑系统,结合钢桁架操作平台和模板平台,钢桁架在下横梁顶部拼装完成后整体提升至高空安装的施工方案。确定桁架系统选型后,用有限元软件Midas/civil计算其应力和变形,确保满足要求,并提出桁架提升应急预案。桁架现已提升就位,与传统施工工艺比较可加快将近1个月的施工进度。
[关键词] 桥梁;闵浦大桥;上横梁;支撑桁架;整体提升

Design and Construction of Supporting Truss for Upper-beam Bottom Formwork in Minpu Bridge Puxi Segment
 
Abstract:Because of delay induced by removal, Puxi segment of Minpu Bridge is constructed three monthes later than Pudong segment. New construction scheme is adopted in the upper-beam construction of Puxi segment in order to ensure general goal that the bridge should be finished before 2010, that is taking steel truss as supporting system of bottom formwork, and assembling the steel truss on the top of lower-beam according to operation platform and formwork platform, then lifting the truss integrally and installing it at high altitude. After sel
ecting the truss system, its stresses and deformations are calculated by Midas/civil software to satisfy requirements. Furthermore, emergency response plans during lifting are suggested. Compared with traditional construction technology, the new scheme can shorten construction schedule by about one month.
Key words:bridge; Minpu Bridge; upper-beam; supporting truss; integral lifting
主办单位:亚太建设科技信息研究院有限公司 中国建筑集团有限公司 中国土木工程学会    承办单位:施工技术传媒机构
京ICP备17044493号-16

京公网安备 110102000406-6
主编:张可文 电话:010-57368788   编辑部:010-57368789,010-57368790
广告、理事会:010-68300059,010-68330203,010-68341147   邮购及查询010-68341147  传真010-68300061
地址:北京市西城区德胜门外大街36号中国建设科技集团4层   邮编:100120        Email:sgjs@cadg.cn
施工技术网群鼓励技术交流,信息交流。群号:43883790    75228828    新浪微博:@施工技术传媒机构