论文摘要

(华中科技大学,湖北 武汉430074)

[摘要]结构设计时,对象均是使用阶段的成型结构,而施工过程中结构本身及其受力与设计时的状态具有很大差异,对于大跨网壳、桥梁、隧道等重要结构进行施工过程模拟与监测是非常重要的。该文提出了运用ANSYS有限元软件中单元生死高级选项进行施工过程模拟的数值方法,并以某体育馆大跨度焊接钢管拱形网壳结构为例,考虑温度影响对屋盖的施工过程进行了数值模拟,同时对其进行了施工监测。分析结果表明:温度荷载对支座相连的杆件内力影响较大,而对其它杆件影响很小,并与实测结果吻合得较好,验证了施工模拟数值方法的有效性。


[关键词] 网壳结构;施工模拟;数值模拟;施工监测

In structure design,the object is the used structureCompared with the designed structure,the structure characteristics and stress conditions in constructing process are differentIt is significant to simulate and monitor the constructing process of reticulated shell and bridges and tunnelsThis paper proposes a numerical simulation method using the birth & death advanced function of the ANSYS finite element softwareEffects of temperature are considered and the constructing process of the large span reticulated shell of a gymnasium numerical simulation is providedAt the same time, the constructing process was monitoredFrom the numerical results,it is found that temperature load is an important influencing factor members to link connecting with support but the other members are notAnd the results from calculation fit well with the experimental ones,it can be concluded that the numerical method described in the paper is more effectual

主办单位:亚太建设科技信息研究院有限公司 中国建筑集团有限公司 中国土木工程学会    承办单位:施工技术传媒机构
京ICP备17044493号-16

京公网安备 110102000406-6
主编:张可文 电话:010-57368788   编辑部:010-57368789,010-57368790
广告、理事会:010-68300059,010-68330203,010-68341147   邮购及查询010-68341147  传真010-68300061
地址:北京市西城区德胜门外大街36号中国建设科技集团4层   邮编:100120        Email:sgjs@cadg.cn
施工技术网群鼓励技术交流,信息交流。群号:43883790    75228828    新浪微博:@施工技术传媒机构