岩土与地下工程 2026年 第卷 第03期

DOI: 10.7672 / sgjs2026030071

考虑围岩蠕变效应的铣挖法隧道施工变形控制研究

徐占军¹,张威振¹,邹魁¹,黄振华¹,傅鹤林²

作者简介:

徐占军,正高级工程师,E-mail: 244801010@ csu. edu. cn

作者单位:

1.湖南中大设计院有限公司,湖南长沙 410075; 2.中南大学土木工程学院,湖南长沙 410075

基金项目:

∗国家自然科学基金(52478424);中南大学-湖南中大设计院有限公司工程建设设计信息化技术研发中心开放课题(KJ-2025-01)

摘要:

为解决软岩浅埋小净距水下隧道铣挖施工变形控制问题,开展单轴压缩蠕变试验,厘清不同含水状态下泥质粉砂岩蠕变特性。根据泥质粉砂岩蠕变试验数据,采用 Cvisc 蠕变本构模型拟合应力-应变关系,并标定本构参数。通过建立考虑岩体蠕变的数值模型揭示隧道受力与变形特征,并在此基础上优化先后行洞开挖步距、二次衬砌施作时机,将数值模拟结果与现场监测数据进行对比验证。研究结果表明,饱和状态下泥质粉砂岩强度下降,更易产生蠕变变形;Cvisc 模型计算结果更有利于保证施工安全性,更符合围岩力学特性;不同先后行洞开挖步距和二次衬砌滞后施工距离下初期支护混凝土强度均满足施工安全要求,隧道拱顶沉降规律较接近,且拱顶沉降对于先后行洞开挖步距和二次衬砌滞后施工距离的参数敏感性最高,其次依次为拱肩沉降、拱腰沉降、拱底沉降、拱脚沉降;增大先后行洞开挖步距、减小二次衬砌滞后施工距离可有效增强隧道稳定性,控制拱顶沉降;最优先后行洞开挖步距为 39m,最优二次衬砌滞后施工距离为 9m;Cvisc 模型模拟得到的隧道拱顶沉降与监测值误差较小,且变化趋势基本一致,围岩变形最终达到收敛状态。

English:

To address the deformation control challenge in the shallow-buried underwater tunnel withsmall clearances in soft rock excavated by roadheader, uniaxial creep tests were performed to examine thecreep behavior of mudstone siltstone under varying moisture conditions. Based on the experimentalresults, the Cvisc creep constitutive model was adopted to fit the stress-strain relationship, and theconstitutive parameters were calibrated accordingly. A numerical simulation model with rock mass creepwas developed to investigate the stress and deformation characteristics of the tunnel. Using this model,the excavation sequence distance and timing of secondary lining installation were optimized. The resultswere then validated by comparison with field monitoring data. The research results show that undersaturated conditions, the strength of mudstone siltstone decreases, making it more susceptible to creepdeformation. The Cvisc model provides better agreement with the mechanical behavior of the surroundingrock and ensures higher construction safety. Under different excavation sequence distance and secondarylining delay distance, the strength of the initial support concrete meets the safety requirements, and thevault settlement patterns are generally similar. The tunnel vault settlement exhibits the highest sensitivityto excavation sequence distance and secondary lining delay distance, followed by the settlements at theshoulder,waist, invert and foot of the tunnel. Increasing the excavation sequence distance and reducingthe secondary lining delay distance effectively enhance tunnel stability and control vault settlement. Theoptimal excavation sequence distance and secondary lining delay distance are determined to be 39m and 9m, respectively. The vault settlement simulated using the Cvisc model shows minimal deviation from themonitored values,with consistent trends, indicating that the surrounding rock deformation eventuallyconverges.