岩土与地下工程 2026年 第卷 第07期

DOI: 10.7672 / sgjs2026070038

邻近既有建筑深基坑开挖变形特性及支护结构优化分析

张 奎

作者简介:

张 奎,助理工程师,E⁃mail:3950768090qq. com

作者单位:

中铁十八局集团第三工程有限公司,河北 涿州 072750

基金项目:

∗中铁十八局集团有限公司 2024 年度科研创新项目(2024⁃031)

摘要:

通过对邻近既有建筑深基坑工程开展现场实测,并建立相应的基坑开挖三维有限元模型,分析了基坑和既有建筑变形随基坑开挖的变化规律. 研究了不同桩径、桩间距和内支撑水平距离对基坑和既有建筑变形的影响,对基坑支护结构进行了优化. 结果表明,桩体水平位移、既有建筑水平位移和沉降随基坑开挖深度增加而增大,桩体水平位移沿深度方向先增大后减小,最大值出现在深度 16m 处. 既有建筑水平位移随建筑高度增大而增大,沉降随距基坑边缘距离增加而减小. 基坑开挖过程中既有建筑结构较为安全. 桩体水平位移和既有建筑沉降随桩径增大而减小,随桩间距和内支撑水平间距增大而增大. 建议基坑围护桩桩径 1 200mm、桩间距 1 000mm、内支撑水平间距 3m,此时最大桩体水平位移为 30.7mm,既有建筑沉降为 18.4mm,比原支护方案分别减小约 17%和 12%.

English:

Based on field monitoring of a deep foundation excavation constructed adjacent to existingbuilding, together with the establishment of a corresponding three⁃dimensional finite element model of theexcavation, the deformation evolution of both the foundation excavation and existing buildings duringexcavation was investigated. The influences of pile diameter, pile spacing, and horizontal spacing ofinternal supports on the deformation behavior of the foundation excavation and adjacent building wereanalyzed, and the support system was optimized accordingly. The results indicate that the horizontaldisplacement of retaining piles, as well as the horizontal displacement and settlement of existing building,increase with excavation depth. The horizontal displacement of piles first increases and then decreaseswith depth, with the maximum value occurring at a depth of 16m. Larger horizontal displacements of pilesare observed in zones close to the existing building. Horizontal displacement of existing building increaseswith building height, while the settlement decreases with increasing distance from the excavation edge.The existing building remained in a relatively safe condition throughout the excavation process. Both pilehorizontal displacement and building settlement decrease with increasing pile diameter, but increase withlarger pile spacing and greater horizontal spacing of internal supports. It is recommended that theretaining piles adopt a diameter of 1 200mm, a pile spacing of 1 000mm, and an internal supporthorizontal spacing of 3m. Under these conditions, the maximum pile horizontal displacement is 30.7mmand the building settlement is 18. 4mm, representing reductions of approximately 17% and 12%,respectively, compared with the original support scheme.