岩土与地下工程 2026年 第卷 第13期

饱和软黄土深基坑降水开挖施工地表变形特性与参数分析

杜孟飞

作者简介:

杜孟飞,高级工程师,Email:526743462@qq.com

作者单位:

(中国建筑第四工程局有限公司,广东广州510665)

基金项目:

*陕西省重点研发计划(2020SF-373)

摘要:

为探究饱和软黄土深基坑降水开挖施工的地表变形特性,以西安某地铁车站竖井工程为背景,结合现场监测与数值模拟,分析了地表沉降历时变化规律及影响因素。结果表明:地表沉降历时曲线可划分为卸荷隆起、降水固结沉降、变形稳定及水位回升回弹4个阶段,降水施工期是沉降发展的主要阶段。参数分析表明,地表沉降随土体渗透系数增大而增大、随地下水埋深增大而减小;单次开挖深度建议控制在1-4m左右。综合考虑支护效果与经济性,推荐采用I20a及0-8m布设间距。

English:

To investigate the surface deformation characteristics during dewatering and excavation of deep foundation excavations in saturated soft loess, this paper analyzed the temporal variation patterns of surface settlement and their influencing factors based on a shaft project for a subway station in the city of Xi’an, combining field monitoring with numerical simulation. The results indicate that the timedependent curve of ground settlement can be divided into four stages: unloading heave, dewatering consolidation settlement, deformation stabilization, and rebound due to rising water levels. The dewatering construction period is the primary stage during which settlement occurs. Parametric analysis shows that ground settlement increases with an increase in the soil permeability coefficient and decreases with an increase in the depth of the groundwater table. The recommended single excavation depth should be controlled at around 1-4m. Considering both the support effectiveness and the economic efficiency, the use of I20a with a spacing of 0-8m is recommended.